2016 Road Program
This street improvement project includes asphalt pavement removal and replacement, cement treated subgrade, concrete curb and sidewalk, storm sewer improvements, slurry seal, and pavement marking removal.
Status Updates
03/15/2017 - Final punchlist provided to contractors for close items. Project substantially complete.
1/30/2017 - Restoration activities in progress such as shoulder rock and compaction, grouting of new catch basins, setting basin tops to grade, etc.
1/23/2016 - Approximately 75 linear feet of 12" concrete storm pipe installed from new catch basin on Lower Midhill and Robinwood Way intersection south to Lower Midhill. Temporary hot mix placed on trenches within intersection.
11/16/2016 - Storm work in progress. 12" of pvc pipe installed from NE corner to NW corner of Robinwood Way and Lower Midhill.
11/04/2016 - Crews working to correct grade elevation on 9th and 10th St.
10/20/2016 - Cement treated subgrade compacted on Britton.
09/26/2016 - Subgrade prep taking place on 10th St.; base lift paving on Marylhurst Dr. complete.
09/22/2016 - Compaction of base complete on Marylhurst Ct., pavement repairs on Marylhurst Dr. almost complete. Northern repair areas being paved.
06/15/2016 - Contract awarded by Council to S-2 Contractors (lowest responsive bidder)
06/08/2016 - Bid Opening (3 bids received)
05/23/2016 - Advertisement for Bid published
Disclaimer
Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.