2017 Waterline Project

Project ID: 
PW-16-03
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
Complete
Project Budget: 
$699,858.00
Project Manager: 
Erich Lais
Project Contact Information: 
Erich Lais 503-722-3434 elais@westlinnoregon.gov
Project Dates: 
March 24, 2017 - 7/16/2017
Public Notice Deadline: 
Not applicable
Deadline Type: 
none
Neighborhood: 
Robinwood

This waterline replacement project generally consists of installing 3,600 linear feet of 8-inch ductile iron water line and 1,300 linear feet of 12-inch ductile iron water line. Permanent trench paving, hydrant installation, water service connections, surveying, and landscape restoration are also included. 

Status Updates

09/20/2017 - Project complete. Punch list items complete. Restoration for staging area at Robinwood Station is finished. 

08/31/2017 - Project is being closed out. Contractor will be wrapping up punch list items within the next week.

08/02/2017 - Construction wrapping up, equipment being removed from staging areas, site restoration taking place

07/19/2017 - Approved chlorination test

07/18/2017 - Approved pressure test

06/29/2017 - Installation of 1" water services on Kenthorpe. Excavation, pipework and backfilling taking place. All services to be installed by end of month.

05/23/2017 - 482 linear feet of 12" ductile iron installed on Old River and approximately 235 linear feet of 8" ductile iron installed on Kenthorpe Way.

05/01/2017-05/04/2017 - Tie into existing 10' ductile iron pipe on Hillcrest; install last 72 linear feet of 12" ductile iron going south toward Ridgebrook Dr. tie in location. Installation of 1" water services.

04/24/2017 - Installation of approximately 420 ft of 8" ductile iron water main on Valley View

04/17/2017 - Notice to Proceed

02/22/2017 - Notice of Award issued

02/13/2017 - Contract awarded to Oregon Underground Inc.

01/19/2017 - Project advertised for bid

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.