2024 Safe Routes to School- Construction

Project ID: 
PW-24-01
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
In Process
Project Budget: 
$928,816
Project Manager: 
Jameson Lumpkin
Project Contact Information: 
jlumpkin@westlinnoregon.gov 503-722-4739
Neighborhood: 
Robinwood

Construction of sidewalk along the north side of Cedaroak Drive from Trillium to Old River Road for access to Cedaroak Park Primary. In addition to the sidewalk, the project will include storm water planters with trees, the centering the Trillium intersection within the right-of-way, and repaving of Cedaroak. There will also be a Rectangular Rapid Flashing Beacon (RRFB) at the crossing at Trillium and sidewalk to connect to the bike path and bridge to Kenthorpe Way. Sign-up for Email Updates

Status Updates

9/30/2024- Trees and shrubs to be planted in stormwater facilities. Project close out tasks to be completed this week.

9/2/2024- Planting of stormwater facilities expected in early October.

8/12/2024- Paving expected later this week. Following paving RRFB remains to be installed and repair work will be done to some sidewalk panels.

8/5/2024- Crews have been pouring driveways and ADA ramps throughout the project. Sidewalk has been installed at the south side near Trillium and the contractor has poured the bases for storm water catch-basins. Next week, crews will begin installing the curb along the north side of Cedaroak Drive and begin work on the sidewalk. Paving is expected the week after.

7/16/2024- Crews will be doing utility locates and marking over the next few days and the contractor will begin mobilizing in equipment on 7/18.

7/9/2024- City staff attended RNA meeting to go over plans and answer questions.

6/26/2024- City staff met with contractor and work expected to begin 7/10. Contractor will be bringing in supplies and equipment and removing brush from the construction area. 

6/17/2024- Construction contract approved by City Council. 

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.