4120 Mapleton Partition
Related Planning Department project files:
Status Updates
04/02/2019 - Single-family home construction continues.
02/12/2019 - Sidewalk construction will be complete with single-family home construction. All other right-of-way improvements complete.
01/08/2019 - Contractor is working on right-of-way improvements. Sidewalk anticipated to be completed with construction of single-family homes.
11/14/2018 - Contractor is working on sidewalk improvements.
08/15/2018 - Frontage improvements are ongoing.
06/05/2018 - Public improvement work is ongoing.
04/09/2018 - Performance bonds secured.
03/05/2018- Offsite improvement plans approved for construction
Disclaimer
Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.