Bolton Reservoir Replacement

Project ID: 
PW-14-06
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
Complete
Project Budget: 
$8,908,069.47
Project Manager: 
Erich Lais
Project Contact Information: 
Erich Lais 5036-722-3434 elais@westlinnoregon.gov
Project Dates: 
11/30/2015 - 11/01/2017

This project consists of the abandonment and removal of the existing 100 year old 2.5 MG Bolton Reservoir and old pump station building, and construction of a new 4.0 MG prestressed concrete reservoir on the same parcel.  Designs incorporate reservoir sitework, improvements to the existing Bolton Pump Station, bypass piping and upgrades to the associated water system including approximately 3,100 linear feet of 24-inch diameter offsite water main, and construction of approximately 3,800 linear feet of roadway improvements consisting of roadway widening and grading, curb and sidewalk, drainage improvements, retaining walls, asphalt paving, pavement striping and landscaping. 

 

Bolton Reservoir Background Information

Status Updates

4/25/2018 -  Awaiting final sale of adjacent properties that were purchased for construction staging during the project. Council to review offers on May 7th, 2018. 

12/15/2017 - Landscaping is finished. All site restoration complete. Project is substantially complete.

10/17/2017 - Landscaping underway; planting anticipated to be finished by months end. Contractor working on punchlist to wrap up project.

09/20/2017 - Onsite paving complete. Gate entrance installation complete.

08/31/2017 - Permitter fencing installed; onsite paving scheduled for mid-September. Landscaping is scheduled for October with project completion anticipated for November.

08/02/2017 - Water reservoir online and operational. Backfill of reservoir near completion. Final landscaping to take place in the fall.

04/03/2017 - Pre-stressing of the tank underway with continuous wrapping.

12/01/2016 - First half of reservoir roof poured on November 29th. Last wall section is scheduled for December 6th.

07/19/2016 - Excavation completed for the reservoir. Aggregate base installed along the floor drains. First concrete pour for the reservoir scheduled for the end of July.

03/23/2016 - 24" water main installation complete and pending final testing. Reservoir demo to begin after acceptance of waterline.

1/25/2016 - Clearing and cleanup of the reservoir site and Skyline Dr. completed. New 24" mains being installed on Skyline Dr. and at Easy St. and Broadway. Century Link has projected to begin working on utility /relocaions along Skyline near Firwood on Friday, January 22, 2016.

11/30/2015 - Notice to Proceed issued

10/19/2015 - Council awarded contract to Rotschy

 

 

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.